Event x (in
red) = completed |
Pre- 21Jul |
w/c 21Jul |
w/c 28Jul |
w/c 4Aug |
w/c 11Aug |
w/c 18Aug |
w/c 25Aug |
w/c 1Sept |
|
7 active days of week as x’s (dashes denote non-active days) |
xxxxxxx |
xxxxxxx |
xxxxxxx |
xxxxxxx |
xxxxxxx |
xxxxxxx |
xxxxxxx |
xxxxxxx |
|
Bank Hol w/e |
|
|
|
|
|
-----xx |
x |
|
|
Hort Show prep & event |
|
|
|
|
|
|
----xx |
|
|
Flower Club eve use of front 60% - work
equipment at back |
|
--x |
|
|
|
|
|
|
|
DIY Strip hall – store items |
xxx |
|
|
|
|
|
|
|
|
CH drain down ...........Radiators off and
store |
|
xx |
|
|
|
|
|
|
|
Scaffolding to site and erect |
|
x |
|
|
|
|
|
|
|
Pre-plastering joinery (BobDodd) |
|
----x |
|
|
|
|
|
|
|
Electric cables into trunking – cabling ready
for plasterers |
|
---xx |
xxx |
|
|
|
|
|
|
Skylites – basic fitting |
|
xx---x- |
x |
|
|
|
|
|
|
Skylights – internal dressing/blinds/drives |
|
|
-xxxx |
|
|
|
|
|
|
DIY clean ceiling on scaffolding (evening) |
|
|
x |
|
|
|
|
|
|
Plastering (wall prep / board / skim) |
|
|
--xxx-- |
xxx-- |
|
|
|
|
|
Ceiling electrics |
|
|
|
xx--x-- |
x |
|
|
|
|
Velux on-site resolving issues |
|
|
|
|
--x |
|
--x |
|
|
Post-plastering joinery |
|
|
|
---x--- |
---x- |
|
|
|
|
Decoration prep |
|
|
|
----xx- |
|
|
|
|
|
Sand prep floor and first 2 seal coats |
|
|
|
|
xxxxxx- |
|
|
|
|
Floor contingency treatment (wood problems) |
|
|
|
|
-----x- |
|
|
|
|
Badminton lines |
|
|
|
|
------x |
|
|
|
|
Final sand and clean-up ready for top coat |
|
|
|
|
|
x |
|
|
|
Final floor Seal |
|
|
|
|
|
-x |
|
|
|
Clean / diffusers / decoration (scaffolding) |
|
|
|
|
|
--xxx-- |
-x |
|
|
Reinstate wall lighting |
|
|
|
|
|
---xx |
|
|
|
Reinstate radiators |
|
|
|
|
|
|
--xx |
|
|
Final issues incl dado |
|
|
|
|
|
|
xxx |
|
|
DIY clean / re-instate hall |
|
|
|
|
|
|
---x--- |
|
|
DIY remaining hall fixtures |
|
|
|
|
|
|
|