......................Phase 4 - skylights / hall plastering / hall floor - progress reporting


  • on schedule for completion as planned
  • all new skylights fitted and with electric blinds/openers
  • Velux Service on-site 27 Sept to resolve some faults
  • new trunking completed with revised wall electrics
  • all plasterboarded/skimmed and new joinery (incl skirting) complete
  • ceiling now clean - DIY-job removed decades of dust
  • decoration colouring scheme decided - paint acquired via Dulux 'Colour in the Community'
  • floor sanding completed and first sealing coats - top coat planned Tue 19Aug
  • DIY job of marking up new badminton court - caused some problems - but resolved
  • decoration underway from Wed 20Aug
  • .