Early work on 4-SCORE Ph.2 refurbishment supported by
.......... ONYX ......... &..........


Return to homepage

end of day 5 (13Jan06) - detail design on kitchen/bar nearly ready for final approval

end of day 4 - hatches cut into main hall- electrics in main hall ready for uplighters.

...

scroll down for history......

end of day 3 - electrics for kitchen/toilet/entrance - start of toilet partition. detail design finalised for doors

....

end of day 2 - wall fully out / floor part-out / building materials on site. Awaiting final kitchen/bar design for approval.

end of day 1 - old units skipped - start on wall demolition.

morning on 9th Jan 2006...scroll down for more

...... ......