end of day 5 (13Jan06) - detail design on kitchen/bar nearly ready for final approval
end of day 4 - hatches cut into main hall- electrics in main hall ready for uplighters.
scroll down for history......
end of day 3 - electrics for kitchen/toilet/entrance - start of toilet partition. detail design finalised for doors
end of day 2 - wall fully out / floor part-out / building materials on site. Awaiting final kitchen/bar design for approval.
end of day 1 - old units skipped - start on wall demolition.
morning on 9th Jan 2006...scroll down for more ......
......
|