front of the building with some users   

Refurbishment Progress story (wks 5-7).. refurbishment supported by
.......... ONYX ......... &..........


return to homepage

record ...going back in time...

day 33 - toilet decorated awaiting kitting out - new meeting room double doors fitted awaiting glazing & doorhandles (side panels to be varnished to match doors) - small delay on other doors.

One week delay in kitchen/bar construction due to material delivery issue - expect CHR back on site end week 8 (2/3Mar) - vinyl flooring / ceiling and kitting out should then be wk 9 (6-10 Mar) completing bar during wk10.

...

day 30 - (17Feb) - bar roller shutter installed - ready for further joinery on Monday. DBKConstruction - kitchen door glazed and scullery door rehung and partition complete.

..

day 28 - (15Feb) - kitchen fitting slight delay awaiting bar shuttering prior to completion of initial joinery. All kitchen/bar fitting detail now agreed. DBKConstruction - working on decoration & kitchen scullery cupboard - all double door frames awaiting delivery of doors.

day 25 - (10 Feb) - kitchen plumbing - stud frame for kitchen/bar partition - framework for bar grill - toilet window fitted -

day 22 - (7Feb) - walls painted and floor levelled - first fix plumbing - hatch doors in - window cut for new toilet - progress on doorway to meeting room

............

see fourth week

see third week

see second week

see first week & preparation