| Refurbishment Progress story (wks 5-7)..
refurbishment supported by |
return to homepagerecord ...going back in time...
day 33 - toilet decorated awaiting kitting out - new meeting room double doors fitted awaiting glazing & doorhandles (side panels to be varnished to match doors) - small delay on other doors.One week delay in kitchen/bar construction due to material delivery issue - expect CHR back on site end week 8 (2/3Mar) - vinyl flooring / ceiling and kitting out should then be wk 9 (6-10 Mar) completing bar during wk10....
day 30 - (17Feb) - bar roller shutter installed - ready for further joinery on Monday. DBKConstruction - kitchen door glazed and scullery door rehung and partition complete.
day 28 - (15Feb) - kitchen fitting slight delay awaiting bar shuttering prior to completion of initial joinery. All kitchen/bar fitting detail now agreed. DBKConstruction - working on decoration & kitchen scullery cupboard - all double door frames awaiting delivery of doors.
day 25 - (10 Feb) - kitchen plumbing - stud frame for kitchen/bar partition - framework for bar grill - toilet window fitted -
day 22 - (7Feb) - walls painted and floor levelled - first fix plumbing - hatch doors in - window cut for new toilet - progress on doorway to meeting room
see fourth week
see third week
see second week
see first week & preparation
|