Refurbishment Progress story (4th week).. refurbishment supported by
.......... ONYX ......... &..........


return to homepage

day 17 (1 Feb)- damp proof membrane to kitchen floor (final leveling day 18). Skirting boxing of pipes and window architrave.

Meeting Room wider entrance - frames & side panels in place.

...

...

day 15 - drains complete. rebricking around new side entrance. Toilet & kitchen doors. Preparing door frame for Meeting Room entrance.

............

see third week

see second week

see first week & preparation